650 Robertson Ave — City + Funding SOP
Developer SOP Dashboard

650 Robertson Ave — City Engagement + Funding Plan

A practical A-to-Z checklist for moving an owned Charlotte parcel from idea to city feasibility, partner conversations, funding package, and decision gate.

Property650 Robertson Ave, Charlotte NC
Concept4 attached townhomes, approx. 1,600 SF each
Current GoalCity feasibility + funding/partner
Do Not Do YetDo not pay for full construction drawings before feasibility

1. Project Strategy

Core strategy: Since you already own the parcel, your leverage is control of the land. Your next job is to prove the project is buildable, fundable, and profitable before spending heavily on full engineering and construction drawings.

Primary Objective

Engage the City of Charlotte early, identify approval issues, and get enough technical feedback to confidently pitch a partner or lender.

Funding Objective

Prepare a clean deal package that shows ownership, zoning path, rough design, projected costs, projected sales, risks, and requested partner/funding structure.

DoneMajor MilestoneExplicit DirectionStatus
Confirm parcel controlSave deed, tax card, and proof that you own/control the property.
Prepare feasibility packageBuild one clean folder containing property docs, concept plan, budget, and partner summary.
Engage cityAsk for pre-submittal/development guidance before submitting full permits.
Secure funding pathSpeak with lenders, builders, and JV partners using the same deal package.

2. Folder Setup

Create this exact folder structure in Google Drive, Dropbox, or OneDrive.

DoneFolderWhat Goes Inside
01 Property DocumentsDeed, tax card, Polaris report, photos, payoff info, old surveys.
02 Zoning & City ReviewUDO notes, zoning screenshots, city emails, department comments.
03 Concept Site PlanSketches, building envelope, rough site layouts, driveway options.
04 Budget & Pro FormaCost estimates, ARV comps, profit analysis, funding scenarios.
05 Funding PackageOne-page summary, investor deck, lender package, deal terms.
06 Partner OutreachContact list, call notes, emails, follow-up tracker.
07 City CommentsAll City responses, issues, required revisions, decisions.
08 Final PermitsPermits, approved plans, inspection documents, COs.

3. Property Document Checklist

Before you talk to the City or a serious partner, gather the basic property facts.

DoneDocumentWhere to Get ItWhy It Matters
DeedMecklenburg Register of Deeds / closing fileProves ownership and title chain.
Tax CardMecklenburg County property recordsShows parcel ID, assessed value, basic property data.
Polaris Parcel MapMecklenburg Polaris GISShows parcel shape, zoning, approximate dimensions.
Existing SurveyClosing package or prior ownerMay show easements, building lines, utilities.
Photos/VideoTake current photos yourselfNeeded for lenders, partners, builders, and demo estimates.
Mortgage/Payoff InfoLender statementNeeded to calculate real equity and funding gap.
Utility Location NotesCharlotte Water / surveyor / site inspectionDetermines water, sewer, and tap cost risk.

4. City Engagement SOP

Do not ask the City vague questions. Ask specific feasibility questions tied to one concept: four attached fee-simple townhomes, front-load garages, approximately 1,600 SF each.

Step A — Request Pre-Submittal / Development Guidance

Use this message:

Hello, I own 650 Robertson Ave in Charlotte and am evaluating a small infill development concept. The concept is four attached fee-simple townhomes, approximately 1,600 square feet each, three stories, with front-load garages. I am not ready to submit full construction drawings yet. I would like pre-submittal or preliminary development guidance regarding zoning, subdivision, driveways, stormwater, utilities, tree requirements, and any issues that may prevent approval. Can you direct me to the correct process or meeting for preliminary review?

Step B — City Questions Tracker

DoneQuestionDepartmentAnswer / Notes
Is four attached fee-simple townhome development allowed on this parcel?Planning/Zoning
Does N1-C permit this configuration by right?Planning/Zoning
Is subdivision required, and what plat process applies?Subdivision Review
Can all four units use front-load garages and individual driveways?CDOT
Are there driveway spacing, curb cut, or sidewalk conflicts?CDOT
What stormwater review is triggered?Stormwater/Land Development
Are water/sewer upgrades or new taps required?Charlotte Water
Are tree-save or urban forestry requirements triggered?Urban Forestry
What documents should be submitted first?Development Center
What would make the project non-approvable?All Departments

5. Funding Package SOP

Your funding package needs to make the deal easy to understand in five minutes.

DonePackage ItemExplicit DirectionOwner
One-page deal summarySummarize property, ownership, concept, unit count, size, exit, funding need.
Property proofAttach deed, tax card, and parcel screenshot.
Concept site planShow rough layout; label setbacks, footprint, driveways, parking, utilities.
Preliminary budgetInclude acquisition basis, demo, soft costs, hard costs, financing, sales costs, contingency.
Comparable salesFind new/recent townhome sales nearby and calculate likely sales price per unit.
Funding askState exactly how much money is needed and what structure you are offering.
Risk pageList zoning, driveway, stormwater, utility, cost, appraisal, and sales risks.

Funding Structures to Test

Equity Partner

Partner contributes capital. You contribute parcel/control. Profit split after repayment.

Private Lender

Lender funds soft costs and construction. You keep ownership and pay interest/points.

Builder Partner

Builder reduces cash need by building at cost plus fee or profit share.

JV Developer

Experienced developer manages entitlement/design/buildout. You contribute land and share upside.

6. Partner Outreach Tracker

Send a short, clear message. Do not over-explain before you know they are interested.

I own a parcel in Charlotte near 650 Robertson Ave that I’m evaluating for a small infill townhouse development. The concept is four attached townhomes, roughly 1,600 square feet each, with front-load garages. I’m preparing the city feasibility package now and looking for either a funding partner, builder partner, or JV development partner. Would you be open to reviewing the deal?
DoneContactTypeDate ContactedResponseNext Step

7. Preliminary Budget + Pro Forma

Use conservative numbers until real bids come in.

Line ItemEstimated CostNotes / Source
Land Basis / Existing Debt
Survey
Demo
Architecture
Civil Engineering
Permits / Fees
Utility Taps / Upgrades
Construction
Financing Cost
Sales / Realtor / Closing
Contingency
Rule: If the project does not show enough profit after conservative costs and contingencies, do not move to full plans. Redesign, reduce cost, change exit, or find a stronger partner structure.

8. Decision Gate

Green Light Conditions

City says concept is likely approvable.

Survey shows no fatal easement or dimension problem.

Driveways and parking are workable.

Stormwater/utility costs do not kill the deal.

Partner/lender interest is real.

Profit margin justifies risk.

Red Light Conditions

City rejects four-unit concept.

Driveways/frontage do not work.

Utility upgrades are too expensive.

Construction cost exceeds sales support.

Partner terms give away too much upside.

Financing creates too much personal risk.

9. Immediate 7-Day Sprint

DoneDayActionDeliverable
Day 1Create folders and gather deed, tax card, Polaris map, photos, payoff info.Organized project folder
Day 2Contact three surveyors for boundary + topo quotes.Survey quotes
Day 3Create rough concept sketch and one-page deal summary.Concept + summary
Day 4Contact City for preliminary development guidance.City contact/email sent
Day 5Build preliminary budget and funding ask.Draft pro forma
Day 6Identify 20 partners/lenders/builders.Outreach list
Day 7Send first 10 outreach messages and log responses.Partner tracker updated